We are replacing the twin 1.2m culverts in the right of way (ROW) for 129–131A Mairaki Road with a new 3x2m box culvert.
Due to the previous flooding at the twin 1.2m culverts during high rain fall events, we are upgrading this culvert to improve the flows under the ROW to 129–131A Mairaki Road.
The work will include
- Removal of the old 1.2m culverts.
- Installing the new 3x2m box culverts.
Timing of work
We anticipate starting these work on 30 March and should be completed by 10 April.
How the work may affect you
During the work window, vehicle access to the properties past the work site will not be available between 7.30am and 5pm. Temporary vehicle access will be installed outside working hours to the affected properties.
General impacts
Essential services
There will be no planned disruption to your water, wastewater, telephone or power services.
Weather
In the event of bad weather or for unforeseen circumstances, the work may be delayed.
Safety
Please warn your children of the dangers posed by road works. Ensure that they stay well back from the work site and they follow the directions of the workers.
Thank you for your patience while we complete this work. If you have any questions please do not hesitate to contact us.