We are making improvements to the Cones Road drain.

In 2025, Council contractors reshaped the Cones Road drain to improve its capacity during larger rain events and installed two new box culverts. During heavy rainfall in April and May 2025, the drain performed well by conveying a significant volume of stormwater and preventing downstream flooding. However, increased flows and debris from upstream caused some localised damage.

The work will include

The proposed works will repair scour and establish vegetation along the banks to reduce the likelihood of similar damage occurring in future events.

Timing of work

This work will begin 19 January and is expected to take two to three weeks to complete.

Traffic impacts

Two traffic lanes will remain open for the majority of the works. However, there will be times when stop/go traffic management will need to be implemented.

General impacts

Essential services

There will be no planned disruption to your water, wastewater, telephone or power services.

Hours

All work will be undertaken Monday to Saturday, between 6am and 6pm.

Weather

In the event of bad weather or for unforeseen circumstances, the work may be delayed.

Noise and dirt

Road work is a noisy, dirty business — but please bear with us. We will be doing all we can to minimise the impact on your home/business. Your cooperation and patience will help us get the job done as quickly as possible. All work will be carried out between the stated hours and over week days only to help minimise the impact on the community.

Thank you for your patience while we complete this work. If you have any questions, please do not hesitate to contact us.

For more information please contact

Dominic Mansbridge
Project Engineer

Waimakariri District Council
Phone:
0800 965 468
Mobile: 027 827 2683
Email: dominic.mansbridge@wmk.govt.nz

Harri Maguire
Project Engineer

EDR Contracting
Mobile:
021 028 73867
Email: harri@edr.co.nz