Kaiapoi East - New Road Link

Construction of the new road link between Feldwick Drive and Cass Street in the Kaiapoi East Regeneration Area started on 1 February 2018 and was opened to traffic on 6 August 2018. Now known as "Feldwick Drive', all works in the area (and nearby streets) is expected to be completed at the end of September 2018.

August 2018 Update

Feldwick Drive opened all the way through for traffic on Monday 6 August 2018. An official opening was held on Saturday 18 August with over 200 people in attendance and an ‘opening drive’ featuring over forty classic and vintage cars – led off by the Mayor’s classic 1968 Ford Corsair.

Work on the final road repairs near the Kaiapoi East Regeneration Area; in Bracebridge Street, Blackwell Crescent continues and will be completed at the end of September.

Information Notice Bracebridge Street August 2018

July 2018 Update

The new road, Feldwick Drive, is now sealed from Cass Street to Gray Crescent and the new road intersection at Gray Crescent is built. The last section of the carriageway works is underway with the tie-in to the existing Feldwick Drive. A temporary detour will be in place from 16 July 2018 for access to Gray Crescent, Feldwick Drive, Moore Street, Kalmia Place, Kanuka Place and Ellen Place - along the new road via Oram Place.

Information Notice July 2018

June 2018 Update

The Kaiapoi-Tuahiwi CommunityBoard have confirmed the new road link name as 'Feldwick Drive'. The road is expected to be completed towards the end of July, with poor weather conditions in May / June, creating some delays. Residents have been delivered an information notice on 13 June to advise of temporary detours and road closures in place during June and July to allow the work to be completed.

Information Notice June 2018

April 2018 Update

A temporary detour and road closure will be in place for Bracebridge Street and Blackwell Crescent from Thursday 12 April until mid-May 2018. Residents have been delivered an information notice on Friday 4 April.

Information Notice April 2018

March 2018 Update

The road is being excavated between Jones/Cass intersection and Oram Place, and also between Blackwell and Gray Crescents. Drainage installation is underway in these areas. Started constructing pavement between Blackwell Crescent and Gray Crescent i.e. alongside Gray Crescent Reserve and this will be used as a diversion route to allow works on Bracebridge Street. Works on track for completion in mid-June 2018.

January 2018 Update

In late January residents were delivered an information notice to notify the start of works on 1 February with an expected completion of June 2018.

Information Notice January 2018

Background

The Recovery Plan included a new road link between Feldwick Drive and Cass Street. We understand that residents have spent a long time with difficult road conditions and are keen to see permanent repairs made. The approval of the Recovery Plan means this is now possible.

The purpose of the new road is to:

  • Improve access for Kaiapoi East residents
  • Create a low speed and attractive environment
  • Enable walking and cycling
  • Provide access to new reserves.

In 2017, while progressing the design, consents and contract for new road, we were also working with Land Information New Zealand to secure the land to build the road.

New Road

The new road will connect Feldwick Drive (near Gray Crescent), via Bracebridge Street, to Cass Street. The new road will pass along the boundary of Gray Crescent Reserve and the other new reserves.

Jones Street will be repaired later when the design of Cass Street and the mixed use business area is known. This could include a new roundabout at Jones and Cass Street.

The new road will be 6-7m wide, with one lane in each direction. Where the new road meets Gray Crescent, Bracebridge Street, and Oram Place ‘T’ intersections are proposed.

At each of the new intersections there may be a change in road surface (for example pavers). At the entrance to Gray Crescent, Bracebridge Street and Oram Place a raised platform is proposed.

A 3.0m wide shared footpath is planned on one side of the street (next to the new sport and recreation reserve). A mix of shallow grass swales and kerb and channel are proposed for stormwater drainage.

Parking is provided on both sides of the new road. On the southern side, angle parking is proposed. On the northern side, parallel parking is proposed. This parking could be used by people visiting the reserves.

Trees will be planted on both sides of the road. During the consultation (see Community Feedback below) on the design of the new road link between Feldwick Drive and Cass Street we received some feedback on what trees might be planted. Construction of the new road link is expected to be completed next year and street trees will be planted in the next planting season after construction is finished.  We asked for community feedback from 1 to 28 February 2018 about the tree species proposed to be planted. See below Community feedback - Street trees (February 2018).

Street trees – Kaiapoi East new road link (pdf, 3.4MB)

LetsDoKaiapoi_EastNewRoadLink_MAP

Click image to enlarge

KaiapoiEastNewRoadLink_CrossSections

Click image to enlarge

Timing

The construction of the new road link will start on 1 February 2018 and be finished by mid-August 2018.

Additional road works - Bracebridge Street, Blackwell Crescent and Moore Street

Additional works have been awarded to Texco Excavating Ltd to complete as part of the current contract. The following works
will commence on 23 July 2018 and be completed by the end of September 2018.

  • Construction of a cul-de-sac head on Moore Street at the Shiels Place intersection. This site includes the renewal of the existing kerb & channel, and footpath in Moore Street, between Ngaio Lane, up to the Shiels Place cul-de-sac head, and back down to Moore Street to Rowan Lane.
  • Construction of a cul-de-sac head on Blackwell Cres, outside No. 25 Blackwell Crescent. This site includes the renewal of the existing kerb and channel, and footpath in Blackwell Crescent up to Bracebridge Street.
  • Renewal of the existing kerb and channel, and footpath in Bracebridge Street between Blackwell Crescent (north) and No. 44 and 23 Bracebridge Street. This portion of work also includes a section of under-channel storm-water pipe. There will be a short section of existing kerb and channel remaining between the new access road, and Blackwell Crescent.

Other infrastructure works

A new water trunk main (underground pipe) will be installed in the roads along the northern edge of the Kaiapoi East Regeneration Area from Williams Street to Beach Road. This water main will replace abandoned mains and provide a more reliable and resilient water supply. It will also improve the fire-fighting capacity for the area. These works started in May 2017 and were finished in late 2017.

New and replacement sewer mains (underground pipes) will be installed to service properties north of the Kaiapoi East Regeneration Area. A new wastewater pump station will also be built on Feldwick Drive near Gray Crescent. These works will greatly improve the reliability of the wastewater system, and it will no longer rely on damaged sewer pipes that pass through the regeneration area. These works started in June 2017 and were finished late 2017.

Council will also be undertaking some minor road works. This includes installing turning heads at Moore Street (near Shiels Place) and at Blackwell Crescent (near Gray Crescent Reserve). This will make these no-through roads. These works are expected to start in August 2017.

Community feedback - street trees (February 2018)

We asked the community for feedback from 1 February to 28 February 2018 on the tree species proposed to be planted in the road reserves alongside the new road from Feldwick Drive to Cass Street. Information flyers were delivered on 1 February 2018 to the residents living in this area. The flyers will provide details of the proposed trees and a map showing where they will be planted. We received one submission endorsing the proposed tree species.

Street trees – Kaiapoi East new road link (pdf, 3.4MB)

Community Feedback - roading design (May 2017)

We asked for community feedback on the roading design from 2 May to 24 May 2017.

We received seven written submissions (from eleven people), and twenty nine people attended two community drop-in talk meetings. In summary;

One written submission directly supported the new road link, stating they preferred the new road link to Cass Street rather than Charles Street.
Three written submissions directly supported the roading design, noting specific concerns about the tree species, raised platforms and road narrowing.

Nineteen people (includes written submissions and commenters at the community meetings) neither directly supported or opposed the roading design, but raised concerns covering; roading design, wastewater pump station, trees, sport and recreation reserve.

You can read the consultation feedback and the staff response here:

Consultation Feedback (pdf, 254.5 KB)