Water Main Renewal - Cridland Street East, Kaiapoi

The existing water mains on the south side of Cridland Street East are due for renewal as part of this year's Kaiapoi water renewals program.

The existing water mains from 46B Sidney Quay to 19 Ranfurly Street were installed in the 1970s and are in poor condition. A new water main is to be installed to replace these existing assets. All properties supplied from these water mains will have their connections transferred to the new mains.

The work will include

  • Installation of a new water main from 46B Sidney Quay to 19 Ranfurly Street on the southern side of Cridland Street East
  • New lateral connections will be installed at the service box at the property boundary, which will also be upgraded if required.

Timing of work

Work is scheduled to occur in early March 2025, and expected to be completed by April 2025.

How the work may affect you

Water services may temporarily be suspended while connecting the new water main to the existing network.

Traffic impacts

This work will be carried out by closing the southern lane of Cridland Street East.

General impacts
Notice of changes in traffic management
We will do our best to give you enough notice to adjust to any changes in traffic management, please keep an eye out for more updates.

Hours
All work will be undertaken between 7.30am to 5pm.

Weather
In the event of bad weather or for unforeseen circumstances, the work may be delayed.

Safety
Please warn your children of the dangers posed by road works. Ensure that they stay well back from the worksite and they follow the directions of workers.

Thank you for your patience while we complete this work. If you have any questions please do not hesitate to contact us.

Contact information

Name: Caitlin Roberts | Project Manager