Update: The traffic signals at Ohoka Road/Island Road are now operational.
4 June 2024The traffic signals at Ohoka Road/Island Road are now operational. |
29 May 2024The Traffic Signals at Island Road / Ohoka Road are due to be tested tommorow morning (30 May 2024) around 9am. If everything runs well no minor works are required then they are likely to be officially commissioned. If minor works are still required then they are likely to be commissioned on Tuesday 4 June 2024. |
13 May 2024The closure of Island Road is changing back to the south side of Ohoka Road next week to finish the surfacing works, road marking and sign installations. |
28 March 2024
There will be a road closure on Island Road (South) from Tuesday 2 April to Friday 5 April. This closure is necessary to allow for sealing work on the new traffic signals being installed at the intersection of Island Road and Ohoka Road.
- Closure Dates: Tuesday 2 April to Friday 5 April
- Backup Dates: Saturday 6 April and Sunday 7 April (in case of bad weather or unexpected events)
Additional Information:
- Left turns will not be allowed from the SH1 Ohoka Road off-ramp during off-peak hours (approximately 9am to 2pm) on Tuesday 2 April only.
21 February 2024
The intersection has been flagged as high risk due to the increasing traffic volumes, wait times and the potential for serious crashes.
We expect the project to be completed by the end of May 2024.