Processing Timeframes


Submitting compliant applications with an appropriate lead-time is an important part of making sure an activity goes ahead as planned. While we reference minimum lead-times, we strongly encourage that people involved in this process plan for larger lead-times which should account for any unexpected delays in approval e.g. coordination with other contractor approvals.

The timeframes below are minimum lead/processing times for CAR and TMP applications.

ApplicationMinimum Timeframe
Standard CAR or TMP

5 working days

Project CAR

15 working days

Non-event Road Closure TMP

10 working days**

Event Road Closure TMP

42 days

** This allows for 5 working days to process the TMP and 5 working days to establish the static warning signs.