The upgrades are intended to improve wastewater network capacity and support future servicing requirements in the area.
The work will include
- Trenching up to 2m deep within the road corridor to install the sewer pipe
- Installation of the sewer laterals up to the property boundaries on the western side of the properties
- Reconnecting some of the existing sewer laterals to the new pipe (this will only be applicable to certain properties, and we will work closely with affected residents to minimise disruption).
Timing of work
The contract has been awarded to EDR Contracting Limited. The anticipated start date for the work is late November 2026. Subject to weather conditions and any unforeseen circumstances, the work is expected to take approximately 10 weeks, excluding the holiday period.
Once the contract has been formally awarded, the contractor will confirm the specific commencement and completion dates.
How the work may affect you
The following impacts are expected:
- Potential restrictions to the on-street parking
- Temporary traffic management that might cause delays
- Some driveways may have temporary vehicle access restrictions during work hours. This will only affect certain properties; we will work closely with the affected residents to minimise disruption.
Traffic impacts
Temporary traffic management will be in place. The appointed contractor will contact you with further specific information.
General impacts
Hours
All work will be undertaken Monday to Friday, between 7am and 6pm.
Kerbside collections
Your kerbside collections will remain unchanged. Please ensure your bag or bins are in their usual spot on collection day.
Notice of changes in traffic management
We will do our best to give you enough notice to adjust to any changes in traffic management, please keep an eye out for more updates.
Weather
In the event of bad weather or unforeseen circumstances, the work may be delayed.
Safety
Please warn your children of the dangers posed by road works. Ensure that they stay well back from the work site and they follow the directions of the workers.
Noise and dirt
Road work is a noisy, dirty business — but please bear with us. We will be doing all we can to minimise the impact on your home/business. Your cooperation and patience will help us get the job done as quickly as possible. All work will be carried out between the stated hours and over week days only to help minimise the impact on the community.
Easy does it
Bitumen, concrete and other road repair materials require a bit of care after they are applied. Please treat all new surfaces with extra care following the completion of this project.
Thank you for your patience while we complete this work. If you have any questions please do not hesitate to contact us.

For more information please contact
Teif Matthews
Senior Projects Engineer
Waimakariri District Council
Phone: 0800 965 468
Mobile: 027 212 3136