Road Repairs – 652–688 Lineside Road Rangiora

During recent works along this section of road, two asphalt surface areas were identified as requiring further remediation to future-proof and allow for a smoother ride.

The work will include
  • Relaying sections of asphalt road surface.
  • Linemarking.
Timing of work

Weather allowing, the repair work will take place between Tuesday 7 and Friday 10 April. Work is expected to be completed on the same day.

How the work may affect you
Traffic impacts

While repairs are taking place a lane shift will be in place along Lineside Road. Two-way traffic and access to businesses will be maintained at all times.

Please take extreme care as cyclists will be merging with traffic.

General Impacts

Although we will try to minimise disruption, there will be some noise due to construction and the presence of heavy vehicles.

Thank you for your patience while we complete this work. If you have any questions please do not hesitate to contact us.

For more information please contact

Tim Doornkamp
Project Engineer

Waimakariri District Council
Phone: 0800 965 468
Mobile: 027 201 2703
Email: tim.doornkamp@wmk.govt.nz

Jeremy Rintoul
Business Unit Manager

Schick Civil Construction
Mobile: 021 223 3926
Email: jeremy.rintoul@schick.co.nz