New Sewer Pipeline Installation at Tram Road, Mandeville

Published: 05-Apr-2017

A new sewer pipeline will be installed on the southern side of Tram Road between No. 10 Road and McHughs Road.

What

On Grade Drainage & Excavation Ltd will be starting work on Monday 10 April and the work is expected to take approximately eight weeks to complete.

How this work may affect you

  • The pipeline route crosses McHughs Road, Pinewood Close and a number of driveways. There will be short times when access to your property is limited. We will advise you in advance before any access restrictions.
  • The pipeline will be located in the grass berm. Traffic disruption on Tram Road will be minimal, although lower speed limits will be in place through the works.
  • Due to the location of underground services within the work area, there may be disruption to your telecommunications, power and water. In conjunction with network operators, we will advise you when service interruptions will occur. We will do our best to keep any disruptions to a minimum. 

201703IN-NewSewerPipelineInstallationTramRoadMandeville 

General Impacts

Hours
All work will be undertaken between 7am and 6.30pm, Monday to Saturday.

Weather
If bad weather is experienced or for unforeseen circumstances, the work may be delayed.

Safety
Safety is important to us. Please keep clear of moving machinery. If you need assistance through the work site, please signal a team member who will be happy to help you.

Noise and dust
Noise, dust and vibration will be minimised as much as possible.

Thank you for your patience while we complete this work.

For further information please contact

Alicia Klos
Project Engineer
Waimakariri District Council
Phone: 0800 965 468 (0800 WDC GOV)
Email: alicia.klos@wmk.govt.nz

Jordan Dunfoy
Site Foreman
Ongrade Drainage and Excavation Ltd
Phone: 027 411 4116

Ric Barber
General Manager
Ongrade Drainage and Excavation Ltd
Phone: 021 0263 1834
Email: ric@ongradedrainage.co.nz