Rebuilding Courtenay Drive

Let's Do!

The rebuild of the earthquake-damaged parts of Courtenay Drive, Charters Street and Wyber Place in Kaiapoi. started on 22 January 2018, with completion expected to be in early May 2018.

Information notices (pdf, 244KB) were delivered to the residents in the area in mid-January.

Temporary closure of part of Courtenay Drive

15 March 2018 - There will be a temporary closure to all motor vehicles on Courtenay Drive from Charters Street to 24 Courtenay Drive. This is in place from 7am Monday 19 March to 5pm 4 May 2018. Affected residents will be notified on 15 March 2018.

20 March 2018 - The closure swap intended for 7am Monday 19 March, will now be in place from later this week. Work on the sealing and berms reshaping are being finished this week.

Please note exclusions apply to Fire Service, Ambulance, Police, Council vehicles and other vehicles authorised by the Council.

March 2018 Update

The section of road on Courtenay Drive between Charters St and Wyber Pl is nearing completion (temporarily closed). Road and paths will be sealed on Tuesday 13 March 2018. A few days later this section will be opened for vehicles so the road closure can be moved west of Charters Street to commence road construction there. Charters Street residents will have access from the south and will be informed of the road closure swap a few days in advance. Existing kerbs and path have been demolished in Charters St and contractor will start preparing kerb foundation next week, begining 12 March 2018. Works on track for completion in May 2018.

Background

In December 2016 the Waimakariri Residential Red Zone Recovery Plan (the Recovery Plan) was approved. Now that it has been approved, the rebuild of Courtenay Drive and adjoining roads can get underway.

From 5 February to 4 March 2016 we asked the community for feedback on options for the rebuild of Courtenay Drive. One option was to rebuild Courtenay Drive on its current alignment, with some changes to the street design. Another option was to relocate Courtenay Drive between Charters Street and Wyber Place to run closer to the neighbouring community.

Ultimately the option adopted was to keep the road on the existing alignment. The key advantages of this option are that it costs about $1.3 million dollars less than relocating the road, and means that the underground services (such as water, sewer, stormwater, power, and communications) do not need to be moved.

The rebuild of Courtenay Drive, on its current alignment, was confirmed in the Recovery Plan. The Recovery Plan also shows a mix of rural activities and public space (Heritage and Mahinga Kai Area) on either side of Courtenay Drive.

Repair works

Courtenay Drive will be rebuilt on its current alignment and will be 8m wide, with one lane in each direction. Along with replacement streetlights there will be a 2.5m wide shared footpath on one side of Courtenay Drive and a 1.8m path in Charters Street. There will be kerb and channel on both sides of the road.

Entrance ‘gateways’ are proposed where Courtenay Drive and Charters Street meet the residential areas. At these gateways the road narrows, but still maintains two-way traffic. There is a change in road surface (pavers may be used for example) along with plants and trees to enhance visual presence.

This narrowing and textured surface tells drivers that they are moving into an urban environment.There will also be pedestrian islands in the middle of Courtenay Drive to help people cross and link with key walking routes.

Trees

About 24 trees on the south-west side of the street between Douglas Dawson Place and Wyber Place have been removed to enable the shared path to be built. These trees were inspected earlier in 2017 and most were found to be in poor condition.  New trees will be planted after the road rebuild has been completed in the next planting season.

In February 2018 we sought feedback from the community to let us know their opinion about the species proposed to be planted. See below: Community feedback - street trees (February 2018).

Timing

The rebuild of these roads started on 22 January 2018, with completion expected to be in early May 2018.

As reported in May, asbestos was discovered in the lower layers of the road pavement on Courtenay Drive and Charters Street while excavating for sewer replacement works. A specialist sub-contractor was engaged to safely remove the contaminated material so that the sewer works could continue. Asbestos removal is an expensive activity and one that is best avoided from an environmental viewpoint. Council engineers have been working to redesign the road reconstruction works to minimise the potential for further disturbance of the asbestos - this has contributed to the delay in the roading project getting underway.

Community feedback - street trees (February 2018)

We asked the community for feedback from 1 - 28 February 2018 on the tree species proposed to be planted in the road reserves alongside the repaired Courtenay Drive and Charters Street. Information flyers were delivered on 1 February 2018 to the residents living in this area. The flyers will provide details of the proposed trees and a map showing where they will be planted. We didn't receive any feedback for this consultation.

Street trees – Courtenay Drive and Charters Street (pdf, 801KB)

Community feedback - roading design (May 2017)

We asked for community feedback on the roading design from 2 May to 24 May 2017. We received one written submission who supported the roading design, and raised a concern about the road surface. You can read the consultation feedback and the staff response here:

Consultation Feedback (pdf, 231.3 KB)